Air-conditioning upgrades funded by Austin ISD's $2.44 billion 2022 bond did not start as scheduled this year at four schools, district officials said. Three of them have reported problems with those systems as temperatures topped 100 degrees.
Officials blamed the delays on long equipment delivery times, design requirements and coordination with other campus construction.
What's happening: Bond HVAC work did not start as scheduled at Kealing Middle School, Kiker and Baranoff elementary schools, and the Liberal Arts and Science Academy, or LASA, Executive Director of Facilities David Simon and Executive Director of Construction Management Michael Mann told Community Impact. Kealing, Baranoff and LASA are among 11 AISD campuses that have reported HVAC problems this school year, the officials said.
What's next: The district's September 2025 and January 2026 bond schedules show more than a dozen bond-funded HVAC projects pushed back, 10 of them by a year or more. The officials did not say which campuses' issues remain unresolved, and the district did not respond by press time on whether a revised targeted schedule exists.