Plans for a 6.3-acre “Park Phase” project for The Dwelling are being updated, a spokesperson for the church confirmed via email Oct. 14.
The details: As previously reported by Community Impact, The Dwelling’s Park Phase will include:
Sodded community sports fields
A covered pavilion with restrooms
A driveway and parking areas
Retention and detention areas
Under the new project plans, the pavilion will be enlarged, requiring some re-engineering and permitting, the spokesperson said. Originally expected to wrap up in October, work is now estimated to be completed by the end of 2026.
Some context: Construction began on the Park Phase project in June, as previously reported. Future phases of construction are planned to include a playground and a new ministry facility for community events and worship.