Montgomery is moving ahead with its next water plant after the City Council awarded an approximately $8.35 million construction contract Sept. 22.
Council approved awarding the Water Plant No. 4 project to Schier Construction Company for $8,354,190 and authorized the city to execute the contract. The vote passed without opposition.
What you need to know: The project will include a new water well and elevated storage tank as the city adds capacity to its water system.
Diving in deeper: Council also discussed the construction timeline. Officials said the city initially considered requiring completion within 420 days but received feedback that contractors could increase their bids to account for the tighter schedule.
Instead, the contract allows 500 calendar days and includes $2,500 in liquidated damages for each day the project runs beyond that deadline.
Officials said the project is funded through the city’s 2026 certificates of obligation and work can move forward once the contract, insurance, bonding and other required documents are completed.