Neighbors are challenging two state construction stormwater permits tied to a proposed Cedar Creek data center development, while Bastrop County commissioners tabled a request for expanded authority over large-scale industrial projects.
How we got here: Filed with the Texas Commission on Environmental Quality, permits identify a 304-acre portion of the broader 2,842-acre data center and Pacifico Energy power development as the BCG Cedar Creek Campus headed by Black Chamber Partners—an affiliate of hyperscale data center developer BlackChamber Group.
What's happening? Jamey and Julie Jenkins and Jereme and Katie Lewis, whose properties are surrounded by the proposed development, filed motions July 20 asking TCEQ to overturn the permits, citing drainage, hydrology and stormwater runoff concerns.
The Black Chamber permit lists an estimated construction period of Sept. 1, 2026, through Oct. 1, 2028. According to TCEQ, the agency generally has 45 days to act on a motion to overturn; if it does not, the motion is denied.
What else? Bastrop County Commissioners on Aug. 10 again tabled a resolution that would declare the county's limited authority and ask the Texas Legislature for expanded powers over large-scale industrial projects, such as data centers.
Bastrop County spokesperson Lyndsey Schroeder said the tabled resolution will return during the Aug. 24 meeting at 9 a.m. in the Bastrop County Courthouse at 804 Pecan St.