Progress is continuing on Leander ISD's next two elementary schools after the board of trustees approved the maximum guaranteed construction costs for both projects Nov. 12. Elementary 31 has an approved construction cost limit of $66.7 million, while Elementary 32 has a limit of $62.8 million.
Some context: Elementary 31 and 32 were both approved under Proposition A in the 2023 bond.
Elementary 31 is intended to add capacity in the northeast part of the district, including the Tarvin, Parkside and Akin elementary feeder area.
In October, Chief Operations Officer Jeremy Trimble presented a plan that would relocate the existing Mason Elementary community to Elementary 32, which will be built within the Travisso community. According to district data, only 24% of students zoned to Mason live in its immediate area, while 51% live within the Travisso corridor.
The action taken: The board ultimately voted 4-2 on the maximum guaranteed construction costs, effectively pushing construction forward for both campuses to open by the 2028- 29 school year.