Over 14 months after voters approved a $480 million road bond package for Montgomery County and the first batch of funds was made available to commissioners, the Precinct 2 Commissioner’s Office has nearly completed all of its bond projects.
The big picture: Twelve of the 19 road projects involving widening and restructuring roadways have been completed, per a status update from Commissioner Charlie Riley’s office. Of the remaining projects, five are under active construction and two are waiting to begin construction.
Precinct 2 was awarded $120 million from the 2025 bond to complete the projects. Staff said the ability to move quickly on so many of the projects came from staying in active communication with potential contractors as soon as funds were available for projects to begin work.
Stay tuned: Precinct 2 staff said the next projects the office will be focusing on include the Magnolia Relief Route, Woodtrace Boulevard expansion and extending FM 149 to Hwy. 249.