Check out three Northwest Austin transportation project updates.
Burnet Road Mobility Program
Project: The project will feature updated traffic signals, improved crossings, bus stop improvements, trail connections, shared-use paths and more on Burnet Road from White Horse Trail to US 183 (C2), Bright Verde Way to MoPac (C3) and US 183 to Bright Verde Way (C4).
Update: An August update from city officials stated that construction on all three segments is underway as of early June.
Spicewood Springs Road Regional Mobility Project
Project: The project includes widening the two-lane road into a four-lane road with left-turn bays, creating two water detention ponds and shared-use paths, and improving the storm drain system and wastewater lines.
Update: An Aug. 11 update from the city stated that weather-related delays pushed the project's substantial completion to summer 2027. Starting in September, work will be underway on shared-use pathways on both sides of Spicewood Springs Road.