Demolition work on the site of Bellaire’s soon-to-be-built south detention basin is nearing completion, City Manager Sharon Citino confirmed in a Sept. 14 update.
Why it matters: The ongoing site work is among several construction-related tasks within the Cypress Ditch Regional Flood Mitigation Program, an initiative centered around improving the city’s overall drainage capabilities and reducing flooding during heavy rain events.
Latest update: At the Sept. 14 council meeting, Citino shared that all of the site’s former structures have been torn down, leaving only debris removal and final site clearing as the remaining tasks before construction can begin.
The city manager added that since the project’s last update, privacy screening was installed along the site’s fence to ensure the safety and protection of the neighboring synagogue, Congregation Beth Yeshurun.
Looking ahead: In an email to Community Impact following the council meeting, Bellaire Community Relations Administrator Cheryl Bright confirmed that the estimated start date for construction of the south detention basin is early 2027.