A proposed utility project along East Hudgins Street in Grapevine is expected to begin next month.
Grapevine City Council approved up to $660,000 from the utility enterprise fund during the July 21 meeting. The contract, which is worth $594,264 with a contingency of $65,369, was awarded to Fort Worth-based contractor RUTS Construction.
Staff rounded the maximum expenditure up to $660,000, according to city documents.
The overview: The project will include new water and sewer mains along East Hudgins Street between South Dooley Street and South Main Street. Crews will install 1,500 feet of 8-inch water main and 1,500 feet of 8-inch sewer main along the roadway, per city documents.
Following the completion of the utility work, crews will reconstruct East Hudgins Street.
During the project, no traffic will be able to access the project area, according to city documents.
Looking ahead: Construction is expected to begin in mid-August and the contractor has 75 calendar days to complete the project, per city documents.
|