Throughout the week of July 27, drivers should expect a full week of closures on Harvey Road during the "Big 6" construction.
What you need to know
- July 27: Full closure of the southbound main lane from Barron Road to William D. Fitch Parkway, 8 p.m.-6:30 a.m.
- July 28: Single-lane closure of the southbound main lane from Harvey Road to Rock Prairie Drive, 7:30 p.m.-6:30 a.m.
- July 29-31: Single-lane closure of the northbound and southbound main lanes from Harvey Road to Rock Prairie Drive, 7:30 p.m.-6:30 a.m.
What’s next: The Texas Department of Transportation will be maintaining two open main lanes in each direction during construction. A majority of the work will be on the main lanes, along with the construction of temporary pavement and retaining walls.
|