Officials broke ground Oct. 19 on extensive utility upgrades across Austin-Bergstrom International Airport.
The details: The Utility Infrastructure Campus-Wide, or UICW, initiative is part of the broader Journey With AUS airport expansion program and is expected to be completed in 2029.
What happened: The groundbreaking came as UICW project costs rose from $120 million to $344 million, a jump of more than 180%. City Council authorized that increase Oct. 22 after the airport's planned future footprint had grown from an anticipated 20 new gates to 32 since UICW project design work began.
Zooming in: The multi-billion dollar expansion program is funded by airline charges, airport cash reserves, revenue bonds and federal grants, with no city tax dollars used.
Contractors Sundt Construction, Inc. and Archer Western Construction will deliver UICW improvements including:
A new electrical system and power distribution center
New storm drainage, and water quality and detention ponds
Hydronic piping for hot and chilled water
New information technology and telecommunications duct banks