West University Place officials authorized the issuance of a Construction Manager-at-Risk, or CMAR, Pre-construction Phase contract with RAVA Construction, LLC, on Oct. 26 for the first phase of work related to the Milton Water Plant Improvements Project.
The motion to award the Houston-based general contractor a fixed fee of $190,417 for pre-construction services passed in a 4-1 vote, with council member Kalie Rainsberger voting no.
Why it matters: The improvements project seeks to upgrade West U’s nearly 70-year-old water plant located at the intersection of Milton Street and College Street.
Based on the results of past studies conducted by officials, the Milton Street Pump Station lacks sufficient space to update its pump capacity without having to take the entire station offline. Doing so would significantly impact and disrupt water service delivery to all residents in West U, according to information posted on the city website.
The gist: RAVA will undertake a dual role as West U’s consultant during the pre-construction phase and, potentially, as its general contractor during the construction phase, per the presentation.