Stay updated on seven road and sidewalk projects in Grapevine, Colleyville, Southlake and Dallas Fort Worth International Airport.
Upcoming projects
Austin Street repairs
Project: The project provides for the reconstruction of 800 linear feet of road, including new curbs and gutters, sidewalks, barrier-free ramps and driveway approaches from Franklin Street to where Austin Street dead ends at the TEXRail railroad tracks.
Update: The city of Grapevine approved a contract for road work at the Feb. 17 council meeting.
- Timeline: project to begin in May and take six months to complete
- Cost: $683,520
- Funding sources: city of Grapevine, Tarrant County
Ongoing projects
SH 360 Repaving: Project: TxDOT is making operational improvements on SH 360, between Stone Myers Parkway and Mid-Cities Boulevard in Grapevine and Euless, to remove a bottleneck that occurs on SH 360.
Update: Nightly lane closures in the northbound and southbound lanes of SH 360 will occur through March 27, from 9 p.m. to 5 a.m.
- Timeline: February-March
- Cost: Not available
- Funding sources: TxDOT
|