An expanded show arena, construction lab and agricultural mechanics lab are among the features included in the early design for Friendswood ISD’s new career and agricultural science center. The board of trustees reviewed the schematic design at its Nov. 9 meeting, but delayed approval for further discussion and to gather additional information about initial costs.
What you need to know: The preliminary design for the career and agricultural science center includes three buildings totaling nearly 42,000 square feet, as well as nearly 10,500 square feet for parking, district documents show.
In their own words: During the meeting, trustee Tony Hopkins raised questions about the project's projected costs and asked for additional information about the initial estimates provided by Huckabee, the project's architectural firm.
Looking ahead: If approved, construction is expected to begin in April and take about nine months, with substantial completion anticipated by late 2027, district documents show.