Check out six upcoming, ongoing or completed transportation projects across the Austin metro.
Ongoing projects
Bell District to 183A Toll shared-use path
Project: Construction is underway on a shared-use path that will connect 183A Toll to Bell Park in Cedar Park. It will be a 10-foot-wide concrete path following along Brushy Creek Road.
Update: According to city officials, crews have begun building the path itself, as well as working on utility relocations and drainage infrastructure.
- Timeline: expected completion fall 2026
- Cost: $3.3 million
- Funding source: 2022 transportation bond
Gattis School Road Segment 6
Project: The project will expand the Round Rock corridor to a six-lane divided arterial between Via Sonoma Trail and Red Bud Lane. Planned improvements include a raised median, intersection upgrades, additional turn lanes, and new pedestrian and bicycle facilities.
Update: Work on the segment began Feb. 2. The initial phase of construction will temporarily reduce the roadway from four lanes to two.
- Timeline: 2026-27
- Cost: $23 million
- Funding source: Type B sales tax revenue
|