Roadwork continues on several projects in the Georgetown area. Recent updates include design work for the ramps at Hwy. 195 and Ronald Reagan, and a recently completed road has gotten a new name.
Find out more about these projects below, as recently confirmed by Williamson County officials.
Ongoing project: Ramps at Hwy. 195 and Ronald Reagan
Project: This project will construct a series of entrance and exit ramps at the intersection of Hwy. 195 and Ronald Reagan Boulevard.
Update: The first northbound exit ramp opened Aug. 24. The engineer for the remaining three ramps is addressing the design alternatives with the final schematic anticipated to be completed in fall 2027.
Completed project: CR 255 (Tucker Parkway) reconstruction
Project: A new two-lane roadway was constructed alongside the existing road from CR 254 to CR 289.
Update: The road opened for drivers Aug. 24. The county renamed the road as “Tucker Parkway.”