Check out five upcoming, ongoing and completed transportation projects in the Dallas-Fort Worth area.
1. Burney Lane/Midway Road rehabilitation
Project: The work will cover the rehabilitation of around 2,950 linear feet of Burney Lane/Midway Road from the intersection of Lonesome Dove Road in Southlake until Meadowmere Lane in Grapevine, according to city documents.
Update: Grapevine City Council approved an interlocal agreement with Tarrant County for the project during a July 7 meeting.
- Timeline: construction estimated to start fall 2026
- Cost: TBD
- Funding source: city of Grapevine, city of Southlake, Tarrant County
2. Ohio Drive and Gaylord Parkway roundabout
Project: A roundabout is being added at the intersection of Ohio Drive and Gaylord Parkway in Frisco.
Update: Traffic in both directions has shifted from using the east half of Ohio Drive to using the west half of the road as of July 9, according to a July 9 city news release.
- Timeline: March 2026-early 2027
- Cost: $3.5 million
- Funding source: city of Frisco, external funding
|