Round Rock officials will consider adding $167,325 to the design contract with Parkhill for improvements to the city’s recycling center during the Nov. 19 City Council meeting.
The big picture: The additional funds would bring the total cost to design the facility updates to $416,825. Funds for the contract supplement would come from the city’s self-financed construction fund, which is generated by local sales tax revenues.
What’s new: Public Works Director Michael Thane said during a Nov. 17 packet briefing that the extra funds are needed to roll new services into the project that were not previously identified.
City documents show these additions include a new pole barn for storage and subsequent engineering, wastewater line service and foundation design.
The barn could partially be converted to a building in future phases, Thane said.
What's next: Once the design is complete for the first phase of improvements to the facility, Thane said the project could go out to bid in mid-to-late 2027.