Check out five upcoming and ongoing transportation projects around Dallas-Fort Worth.
Upcoming projects
1. Plano residential paving
Project: The city will be replacing 4,900 linear feet of street paving, sidewalks and barrier-free ramps, along with 250 linear feet of water line in some neighborhoods near Independence Parkway.
Update: Plano city council approved a construction contract for the project at a June 22 meeting, and work is expected to start in July.
- Timeline: July 2026-summer 2027
- Cost: $2.7 million
- Funding source: city of Plano
2. Legacy Drive widening
Project: Legacy Drive will be widened from Lebanon Road to Stonebrook Parkway. As part of the project, Stonebrook Parkway will also be widened from Legacy Drive to 4th Army Drive. The roadways will also be reconstructed along with the widening.
Update: The project is in the design phase and is expected to start construction later this year.
- Timeline: mid 2026-mid 2028
- Cost: $20 million
- Funding source: city of Frisco
|