Stay informed on five road projects around-Dallas Fort Worth.
Collin County
1. Marilee Road improvements
Project: The project consists of reclamation of the existing asphalt roadway on Marilee Road from Preston Road to Dallas Parkway in Celina. This project will be shared with the city of Gunter, Grayson County, Collin County, city of Celina and the adjacent subdivision developers.
Update: The project is in the design phase and waiting on funding to determine a timeline for bidding.
- Timeline: estimated completion in April 2027
- Cost: $8.7 million
- Funding sources: city of Gunter, Grayson County, Collin County, city of Celina and the adjacent subdivision developers
Industrial Boulevard utility improvements
Project: The planned reconstruction of existing water and sanitary sewer lines will take place along Industrial Boulevard between SH 5 and Airport Drive in McKinney.
Update: Design work is 90% complete, and the project is expected to go to bid later this year.
- Timeline: late 2026-late 2027
- Cost: $9.2 million
- Funding source: city of McKinney
|