SH 5 in McKinney is turning into a 4-lane roadway and a hospital in the Alliance area is expanding its neonatal unit. Check out some of the latest construction projects filed with the Texas Department of Licensing and Regulation.
1. Core Scientific renovations
One of Denton’s two data centers, Core Scientific, will see renovations for a 27,678 square-foot facility to be used as a data hall, according to a TDLR filing.
- Location: 8171 Jim Christal Road, Denton
- Estimated timeline: Sept. 1, 2026-May 31. 2027
- Estimated cost: $110 million
2. New lanes for SH 5 near the McKinney and Fairview border
The Texas Department of Transportation, or TXDOT, is turning a 2-lane roadway into a 4-lane, divided road with a shared use path per the TDLR filing.
- Location: From Spur 399 to south of FM 1378
- Estimated timeline: June 1, 2026-Dec. 1, 2028
- Estimated cost: $60 million
|