Nighttime construction shows improved traffic for daytime commutes and faster construction speed for Plano, according to public works officials.
Drew Zaeske, the public works community investment program manager, provided a presentation about nighttime construction in the city at a meeting Nov. 23.
In a nutshell: Zaeske said the city had two pilot locations for nighttime construction, including concrete replacement at Custer Road and Legacy Drive and along Park Boulevard between Preston Road and Ohio Drive.
Dig deeper: Zaeske said work at the first location took four days, and public works estimated the work would have taken two weeks if it were done in the day time. He said the second location had a larger construction zone and took eight weeks for completion, close to the same as if it were done in the day time.
The background: This year's set of night construction work started in July. The projects are part of a citywide effort to replace concrete roads at main roads, per previous reporting.