Texas’ audit of hundreds of proposed data centers will likely wrap up by the end of the year, grid officials said Aug. 20.
The overview: Up to 300 proposals will be audited to ensure they meet certain criteria before the data centers can begin connecting to the state electric grid. If all the plans are approved, these facilities alone could use about 200 gigawatts of electricity—more than twice Texas’ 91-gigawatt peak demand record, which was set on July 22.
How we got here: On Aug. 3, Gov. Greg Abbott directed ERCOT and the Public Utility Commission of Texas to audit proposed data centers regarding their water and electricity use; tax exemptions; impacts on residents; and facility ownership.
More details: Only large loads, or facilities that are expected to use at least 75 megawatts of electricity, will be fully audited. However, ERCOT will also survey proposed data centers that would use 25 megawatts of electricity or more.
ERCOT plans to release reports detailing the results of the audit and surveys on Dec. 10, officials said.
|