Montgomery County commissioners are slowing the timeline for a justice center bond, deciding not to rush the project onto the May ballot.
During a Sept. 17 workshop, officials agreed they need a clearer picture of long-term courtroom, office, parking and security needs before asking voters for funding.
Diving in deeper: Commissioners asked architects to evaluate if the selected Conroe site can accommodate these long-term needs through 2050, requesting updated square-footage and cost estimates. Department heads and the sheriff's office also requested more involvement to address security, parking and public access.
While a previous $350 million concept proposed 21 courtrooms, County Court at Law No. 2 Judge Claudia Laird noted the county currently needs 23 courtrooms and could require 31 by 2029. Filings are projected to increase by 2050, potentially requiring 35 to 42 courtrooms.
What’s next: BSW Architects will survey county departments, taking about three months to revise the proposal. Commissioners plan to hold another workshop around December or January.